PROJECT LOCATION STATUS OWNER AMOUNT COMPLETION DATE

Green Bay Packaging Under Ground Feeder Replacement

Morrilton, AR Under Construction Green Bay Packaging $2,422,536 October 2012 (estimated)

Pine Bluff Arsenal Smoke Mixer

Pine Bluff, AR Completed Pine Bluff Arsenal $1,242,242 April 2012

US Steel Electrical Distrubution System

Pine Bluff, AR Completed US Steel Tubular Products, Inc $1,587,664 July 2009

LM Wind Power Little Rock Port Site

Port Site - Little Rock, AR Completed LM Wind Power $4,596,483 September 2008

LM Wind Power Celestica Facility

Little Rock, AR Completed LM Wind Power $2,842,643 May 2008

JP Price Sawmill

Monticello, AR Completed JP Price Lumber Company $5,031,340 November 2007

Pace Industries Interruptible Power Design

Harrison, AR Completed Pace Industries, Inc. $259,792 June 2004

Ciba Greenfield Chemical Facility

West Memphis, AR Completed Ciba Specialty Chemicals $3,133,509 September 1999
 
 
 
 